I-0406: Automated Or Manual Recovery Is Acceptable


[The following is the ASCII version of the proposal as posted on Gibraltar. A
pretty-printed PDF version is attached.]

  This transaction consists of a proposal for a National Interpretation of
  a Common Criteria document. It is being posted in accordance with the
  procedures of the IWG.

  Comments on this proposal are welcomed and should be posted to this
  transaction chain.  If any party wishes to post a comment anonymously,
  the comment should be mailed to IWG@gibraltar.ncsc.mil in a form
  suitable for posting.  All comments should be posted no later than
  Monday, February 5, 2001.


                 CCITSE/CEM  NIAP INTERPRETATION (PROPOSED)


     _________________________________________________________________

              I-0406: Automated Or Manual Recovery Is Acceptable
     _________________________________________________________________

NUMBER:               I-0406
STATUS:               Ready for External Review
TYPE:                 NIAP Interpretation

TITLE:                Automated Or Manual Recovery Is Acceptable

SOURCE REFERENCE:     CC v2.1 Part 2 Subclause 10.8 FPT_RCV
                      CC v2.1 Part 2 Subclause J.8 FPT_RCV
RELATED TO:
     I-0389           Recovery To A Known State

ISSUE:

   The current CC v2.1 FPT_RCV.1 elements are worded in such a fashion as
   to preclude the use of automated mechanisms when manual recovery is to
   be supported. This is an unlikely situation; a PP/ST author may not
   care whether recovery is automated or manual.

STATEMENT OF INTERPRETATION:

   Either manual or automated recovery systems are acceptable. The PP/ST
   author has the discretion to specify for what recovery scenarios
   automated recovery is appropriate, and for what recovery scenarios
   manual recovery is appropriate.

SPECIFIC INTERPRETATION:

   To address this interpretation, the following changes are made to CC
   v2.1, Part 2: (additions marked _thusly_; deletions marked _[DEL:_
   thusly _:DEL]_ )


     * In Clause 10.8, delete the existing FPT_RCV.1. As a result of
       this, Paragraph 415 and the "Management" section for FPT_RCV.1 are
       deleted; FPT_RCV.1 is removed from the "Audit" header between
       paragraphs 421 and 422, the "Component levelling" figure is
       modified to delete component 1, and the component decomposition
       figures (Clause 10, Figure 10.1 and Clause J, Figure J.1) showing
       the levelling structure for FPT are corrected to eliminate
       component 1. Additionally, the annex material for FPT_RCV.1 is
       deleted.

     * FPT_RCV.2 is relabeled as FPT_RCV.2-NIAP-0406. Unless otherwise
       noted in these changes, all normative and informative material
       associated with FPT_RCV.2 is incorporated unchanged into
       FPT_RCV.2-NIAP-0406, and all references to FPT_RCV.2 in the CC,
       CEM, or other Common Criteria documentation is changed to refer to
       FPT_RCV.2-NIAP-0406.

     * FPT_RCV.3 is relabeled as FPT_RCV.3-NIAP-0406. Unless otherwise
       noted in these changes, all normative and informative material
       associated with FPT_RCV.3 is incorporated unchanged into
       FPT_RCV.3-NIAP-0406, and all references to FPT_RCV.3 in the CC,
       CEM, or other Common Criteria documentation is changed to refer to
       FPT_RCV.3-NIAP-0406.

     * The "Class Decomposition" figure in Clause 10, Figure 10.1 is
       modified to show component 2-NIAP-0406 as the first hierarchical
       component off of FPT_RCV, with component 3-NIAP-0406 immediately
       hierarchical to 2-NIAP-0406.

     * The "Component Levelling" figure in Subclause 10.8 is modified to
       show component 2-NIAP-0406 as the first hierarchical component off
       of FPT_RCV, with component 3-NIAP-0406 immediately hierarchical to
       2-NIAP-0406.

     * Subclause 10.8, Paragraph 416 is replaced with the following:

     FPT_RCV.2_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery
     from Failure_, provides_[DEL:_ , for at least one type of service
     discontinuity, _:DEL]_ _a specific list (possibly empty) of
     discontinuities for which the TSF must provide the capability for_
     recovery to a secure state without human intervention; recovery for
     other discontinuities may require human intervention.

     * Subclause 10.8, Paragraph 417 is replaced with the following:

     FPT_RCV.3_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery_
     without undue loss, also provides for _[DEL:_ automated _:DEL]_
     recovery _from failure_, but strengthens the requirements by
     disallowing undue loss of protected objects.

     * In Clause 10.8, the following changes are made to FPT_RCV.2:

     FPT_RCV.2_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery
     from Failure_

     Hierarchical To: _[DEL:_ FPT_RCV.1 _:DEL]_ _No Other Components_

     FPT_RCV.2._[DEL:_ 2 _:DEL]_ _1-NIAP-0406_ For [_selection:
     [_assignment: _list of failures/service discontinuities__], "no
     failures/service discontinuities"_], the TSF shall ensure the
     return of the TOE to a secure state using automated procedures.

     FPT_RCV.2._[DEL:_ 1 _:DEL]_ _2-NIAP-0406_ When automated recovery
     from a failure or service discontinuity is not possible, the TSF
     shall enter a maintenance mode where the ability to return the TOE
     to a secure state is provided.

     * In Clause 10.8, the following changes are made to FPT_RCV.3:

     FPT_RCV.3_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery_
     without undue loss

     Hierarchical To: FPT_RCV.2_-NIAP-0406_

     FPT_RCV.3._[DEL:_ 2 _:DEL]_ _1-NIAP-0406_ For [_selection:
     [_assignment: _list of failures/service discontinuities__], "no
     failures/service discontinuities"_], the TSF shall ensure the
     return of the TOE to a secure state using automated procedures.

     FPT_RCV.3._[DEL:_ 1 _:DEL]_ _2-NIAP-0406_ When automated recovery
     from a failure or service discontinuity is not possible, the TSF
     shall enter a maintenance mode where the ability to return the TOE
     to a secure state is provided.

     * The "Class Decomposition" figure in Annex J, Figure J.1 is
       modified to show component 2-NIAP-0406 as the first hierarchical
       component off of FPT_RCV, with component 3-NIAP-0406 immediately
       hierarchical to 2-NIAP-0406.

     * In Subclause J.8, the application notes for FPT_RCV.2 are modified
       as follows:

     FPT_RCV.2_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery
     from Failure_

     _This component requires the TSF to provide mechanisms for
     automated or manual recovery._ Automated recovery is considered to
     be more useful than manual recovery, as it allows the machine to
     operate in an unattended fashion. _However, there may be situations
     where the list of discontinuities that required automated recovery
     is not known in advance, or the PP/ST author does not want to
     mandate automated recovery._

     User Application Notes

     _[DEL:_ The component FPT_RCV.2 extends the feature coverage of
     FPT_RCV.1 by requiring that there be at least one automated method
     of recovery from failure or service discontinuity. It addresses the
     threat of protection compromise resulting from an unattended TOE
     returning to an insecure state after recovery from a failure or
     other discontinuity. _:DEL]_

     _FPT_RCV.2-NIAP-0406 addresses the threat of protection compromise
     resulting from a TOE returning to an insecure state after recover
     from a failure or other discontinuity. It provides the ability for
     unattended recovery for anticipated discontinuities._

     Evaluator application notes

     It is acceptable for the functions that are available to an
     authorised user for trusted recovery to be available only in a
     maintenance mode. Controls should be in place to limit access
     during maintenance to authorised users.

     For FPT_RCV.2._[DEL:_ 1 _:DEL]_ _2-NIAP-0406_, it is the
     responsibility of the developer of the TSF to determine the set of
     recoverable failures and service discontinuities.

     _If "no failures/service discontinuities" is selected for
     FPT_RCV.2.1-NIAP-0406, this means that there are no explicitly
     mandated discontinuities for which automated recovery must be
     provided. The TOE developer always has the option to provide an
     automated recovery mechanism for a discontinuity._

     It is assumed that the robustness of the automated recovery
     mechanisms will be verified.

     Operations

     _Selection:_

     _If there are no explicit situations for which automated recovery
     is mandated, "no failures/service discontinuities" should be
     selected in FPT_RCV.2.1-NIAP-0406. Otherwise, the assignment should
     be selected to provide the list of failures or other
     discontinuities for which automated recovery must be possible._

     _It is acceptable for a PP author complete only the selection and
     leave the assignment open, so as to indicate that the list of
     discontinuities for which automated recovery is required must be
     non-empty._

     Assignment:

     For FPT_RCV.2._[DEL:_ 2 _:DEL]_ _1-NIAP-0406_, the PP/ST author
     should specify the list of failures or other discontinuities for
     which automated recovery must be possible.

     * In Subclause J.8, the application notes for FPT_RCV.3 are modified
       as follows:

     FPT_RCV.3_-NIAP-0406_ _[DEL:_ Automated recovery _:DEL]_ _Recovery_
     without undue loss

     _This component requires the TSF to provide mechanisms for
     automated or manual recovery._ Automated recovery is considered to
     be more useful than manual recovery, as it allows the machine to
     operate in an unattended fashion, but it runs the risk of losing a
     substantial number of objects. Preventing undue loss of objects
     provides additional utility to the recovery effort.

     User Application Notes

     The component FPT_RCV.3_-NIAP-0406_ extends the feature coverage of
     FPT_RCV.2_-NIAP-0406_ by requiring that there not be undue loss of
     TSF data or objects within the TSC. At FPT_RCV.2_-NIAP-0406_, the
     _[DEL:_ automated _:DEL]_ recovery mechanisms could conceivably
     recover by deleting all objects and returning the TSF to a known
     secure state. This type of drastic _[DEL:_ automated _:DEL]_
     recovery is precluded in FPT_RCV.3_-NIAP-0406_.

     This component addresses the threat of protection compromise
     resulting from an unattended TOE returning to an insecure state
     after recovery from a failure or other discontinuity with a large
     loss of TSF data or objects within the TSC.

     Evaluator application notes

     It is acceptable for the functions that are available to an
     authorised user for trusted recovery to be available only in a
     maintenance mode. Controls should be in place to limit access
     during maintenance to authorised users.

     For FPT_RCV.3._[DEL:_ 1 _:DEL]_ _2-NIAP-0406_, it is the
     responsibility of the developer of the TSF to determine the set of
     recoverable failures and service discontinuities.

     _If "no failures/service discontinuities" is selected for
     FPT_RCV.3.1-NIAP-0406, this means that there are no explicitly
     mandated discontinuities for which automated recovery must be
     provided. The TOE developer always has the option to provide an
     automated recovery mechanism for a discontinuity._

     It is assumed that the evaluators will verify the robustness of the
     automated recovery mechanisms.

     Operations

     _Selection:_

     _If there are no explicit situations for which automated recovery
     is mandated, "no failures/service discontinuities" should be
     selected in FPT_RCV.3.1-NIAP-0406. Otherwise, the assignment should
     be selected to provide the list of failures or other
     discontinuities for which automated recovery must be possible._

     _It is acceptable for a PP author complete only the selection and
     leave the assignment open, so as to indicate that the list of
     discontinuities for which automated recovery is required must be
     non-empty._

     Assignment:

     For FPT_RCV.3._[DEL:_ 2 _:DEL]_ _1-NIAP-0406_, the PP/ST author
     should specify the list of failures or other discontinuities for
     which automated recovery must be possible.

     For FPT_RCV.3.3, the PP/ST author should provide a quantification
     for the amount of loss of TSF data or objects that is acceptable.

FURTHER CONSIDERATIONS:

   Other families and components in Part 2 should be examined to correct
   any dependency references to components in FPT_RCV.

PROJECTED IMPACT:

   Negligible impact anticipated.

SUPPORT:

   This reworking of the FPT_RCV elements makes it so that automated
   mechanisms are permitted in all cases, or the PP/ST author has the
   option of indicating the specific situations in which automated
   recovery is mandated.